Darling Park Tower 2 is a NABERS 6 star energy rated building. This project involved the upgrade of a central HVAC plant servicing Tower 2, a 28 story building in the heart of the Sydney CBD.
The $3.4 m project involved a central plant upgrade, replacing 3600kw chiller including 12 cooling towers. This included a full disassemble of existing equipment and rebuild and installation of new equipment in-situ.
Implemented over a nine-month period, with multiple shutdowns and changeovers focused on minimising client disruptions ensuring plant remained operational during critical times.
Tempest Solutions, worked closely with our client, to ensure the project was delivered to their specifications and within key timeframes and budget.