Located within the Nepean Hospital Precinct, the project involved a brand-new medical facility with installation spanning four operating theatres, recovery area, CSSD facilities and overnight patient ward area.
This $1.8 million project involved the installation of 4 Chilled/Hot water Air Handling Units (AHUs),1 Heat Recovery AHU, 18 chilled hot water fan-coil units and multiple ventilation systems and HEPA filters. Precise automation system to comply with close critical control standards.
Tempest Solutions experience and expertise in the delivery and commissioning to regulatory compliance standards was critical to meeting the clients needs. The 5 month project was completed on time and on budget.